CLP India's power project to commence power generation in 2012Illustrative image – not actual.

CLP India is expected to commission a coal based supercritical power project at Jhajjar in Haryana by March 2012.

The 1320 MW power project is slated to have two units of 660 MW each. Techno Electric & Engineering Company, the EPC contractor, is likely to commission the transmission line from Jhajjar to consumption centres at Rohtak and Sonepat in December 2011. The Rs 450 crore transmission project is set up by KT Transco – an SPV created by Techno (49 per cent) and Kalpataru Power Transmission (51 per cent). The construction of the Unit I of 660 MW is expected to be completed soon after the commissioning of the transmission line.