CLP defers Mangalore, Paguthan power projectsIllustrative image – not actual.

In the absence of financial assistance from banks and financial institutions, the Hong Kong-based CLP Power International has decided to put on hold its 1,000 MW Mangalore Power project and the expansion of the 655 MW Paguthan power project.

 

In case of the Mangalore project, CLP Power International has decided to wait till such time as the Karnataka state government, which is currently in the process of reforming the power sector and is also trying to privatise distribution, is successful in putting the reforms on the trail. It may be mentioned that this project was to be executed jointly with the Tata Electric Company.

 

Further according to reports, CLP, which owns about 2,500 MW of installed power capacity in Asia alone, has plans to currently concentrate on improving the functioning of its sole functional asset in India, viz. the Pagathuan project, which it took over from British multinational PowerGen in 2001. Currently, the project is under Gujarat PowerGen Energy Corporation (GPEC), in which CLP holds a majority stake.

 

This project, has however, been facing problems since January 2002, on account of truncated gas supplies from Gas Authority of India, which have been slashed from 1.5 MCMD (million cubic metres per day) to 0.3 MCMD.

 

This has forced GPEC to top up with naphtha only, which has resulted in the power from the plant becoming prohibitively expensive and compelling the Gujarat Electricity Board to suspend purchase of power from the Pagathuan plant, keeping with its policy of merit order dispatch. Accordingly, GPEC has decided to adopt a wait and watch approach till the situation in the power sector improves.

 

It may be mentioned that GPEC had already acquired land and secured in-principle approval of the Gujarat state government for the project. However, the company has not even initiated the process of drafting a PPA (power purchase agreement) or obtaining environmental clearances for the project. The company is of the opinion that till the time that finance is available from banks which would contribute almost 70 per cent of the project cost, there was no point risking the company’s 30 per cent towards the project cost.