Illustrative image – not actual.Oriental Yeast India is setting up a yeast unit with a capacity of 36,000 tpa at Kesurdi in Satara district of Maharashtra.
The project will also include 4.67 MW co-generation power unit. The project worth Rs 709.82 crore will come up over four acre of land area.
In November 2017 Shimizu Corpn India bagged an order for the project. The company awarded the order to Toyo Engineering India for construction of the project. It includes part of detailed design, procurement of equipment and materials (except end user’s free issue materials), installation and commissioning assistance.
In the same month, Oriental Yeast India received approval for the project from the Maharashtra Pollution Control Board.
Following this, the ground leveling work on the project began.
As per the latest update available with Project Today, civil work on the project was progressing as per schedule. The project is expected to be completed by June 2020.
The project will also include 4.67 MW co-generation power unit. The project worth Rs 709.82 crore will come up over four acre of land area.
In November 2017 Shimizu Corpn India bagged an order for the project. The company awarded the order to Toyo Engineering India for construction of the project. It includes part of detailed design, procurement of equipment and materials (except end user’s free issue materials), installation and commissioning assistance.
In the same month, Oriental Yeast India received approval for the project from the Maharashtra Pollution Control Board.
Following this, the ground leveling work on the project began.
As per the latest update available with Project Today, civil work on the project was progressing as per schedule. The project is expected to be completed by June 2020.