Civil work underway on Nagad Narayan Agro Foods’ Bikaner projectIllustrative image – not actual.
Nagad Narayan Agro Foods is setting up a sugar confectionery unit with a capacity of 15,210 tpa at Karni Extension in Bikaner district of Rajasthan. The project will spread over around 30,000 sq mtr land.

The required machinery for the project will be source from Taiwan and China.

The work on the project commenced in March 2015 and environment clearance (EC) was received in April 2015. However, due to some reason the project was kept on hold till June 2017.

The company achieved financial closure for the project in July 2019.

As per information collated by Projects Today, around 45 percent project work has been completed with completion re-scheduled for July 2020. The commercial production is expected to commence by August 2020.