It will have multipurpose cold storage of 3,000 tonne, individually quick frozen and deep freezer of one tonne per hour capacity, sorting and grading yard of 2,000 sq mtr and Food Testing Lab.
The project will spread over 55 acre of land and provide direct and indirect employment to 5,000 persons. The food park was sanctioned by the Central government in March 2015 and by the government of Punjab in the same year in November.
In February 2016, financial closure was achieved for the project. Union Minister of Food Processing Industries Harsimrat Kaur Badal laid the foundation stone for the project in July 2017. The work commenced in January 2018 with completion scheduled for December 2019.
In a recent update shared with Projects Today, it was revealed that civil work on the project was underway with completion pre-scheduled for October 2019.