Illustrative image – not actual.On 3 May 2008, civil works began at NTPC's 3x250 MW thermal power station (known as Bongaigaon Thermal Power Station, or BTPS) at Salakati in Assam.
The Bongaigaon project will use a mix of coal from Eastern Coalfields and from the Margherita fields in Assam. Orders for boilers and turbines have been placed with BHEL. It is learnt that, the proposed power unit will be first in the country to use flue gas desulphurisation technology to control the emission of sulphur dioxide.
Foundation stone for the project had been laid in January 2006 by the Prime Minister, Dr.Manmohan Singh. The first 250 MW is expected to be commissioned in February 2011, the second 250 MW in April/May 2011 and the third unit of 250 MW in June/July 2011.