Illustrative image – not actual.Central India Power Co (Cipco) has
agreed to the escrow protection offered by the Maharashtra State Electricity
Board's (MSEB) for the former's 1,082 MW Bhadravati Thermal Power project
coming up in Maharashtra. The project is estimated to cost Rs.4,636 crore.
As per the draft escrow agreement between MSEB and Cipco, the escrow protection would apply in respect of tariff, termination payments and 50 per cent of the annual Government of India counter guarantee fee. Invalidity or repudiation by MSEB or a collection bank of an escrow document would trigger events. Among other things, MSEB would pay and indemnify Cipco against all taxes and duties payable in connection with the escrow agreement and their enforcement.
All the statutory approvals
including the techno-economic clearance (from CEA) and the environmental
clearance have been received. An agreement is to be shortly concluded with
Western Coalfields Ltd to annually supply 2 million tonnes of coal from Baranj
block and another 2.5 million tonnes from Sasti and Pauni mines.