Illustrative image – not actual.Coal India (CIL) has shortlisted a total of 98 greenfield coal projects which are to be taken up during the Tenth Plan period (2002-07).
These 98 projects envisage a total investment of about Rs.24,082 crore in a phased manner. The combined annual production from these projects at the optimum level will be about 260 million tonnes.
The detailed
project reports for all the new projects have been finalised, and it is now the
responsibility of each subsidiary of CIL to implement these projects.
Opencast mines are
being given priority, with the objective of augmenting production at a faster
rate. Of the total projects shortlisted, about 80 would be in the opencast
category, while the remaining would be small underground mines.
Maximum additional production capacity would be created in three subsidiaries - Mahanadi Coalfields, South Eastern Coalfields and Central Coalfields, in anticipation of higher offtake by thermal power stations.
Details are indicated in the following
table:
|
Subsidiary |
No. of projects |
Capacity* |
|
Mahanadi Coalfields |
19 |
91 |
|
South Eastern Coalfields |
15 |
62 |
|
Central Coalfields |
8 |
42 |
|
Eastern Coalfields |
13 |
24 |
|
Western Coalfields |
29 |
18 |
|
Northern Coalfields |
7 |
13 |
|
Bharat Coking Coal |
7 |
10 |
|
Total |
98 |
260 |
* Million tonnes per annum
Although the mine preparation work on the new projects would begin in 2002-03, most of the projects are expected to give optimum level of production in the Eleventh Plan period. It is thus estimated that these projects, out of the total estimated cost of about Rs.24,082 crore, might require only about Rs.6,220 crore during the Tenth Plan period. Commensurate to investment, additional production from these projects during the Tenth Plan period is envisaged at about 79 million tonnes.