Illustrative image – not actual.CIL has called off preliminary supply agreements with as many as 60 captive power plants (CPP) and independent producers citing that the companies did not comply with the stipulated norms.
The authorisation of LoAs has been called off for non-submission of CG (commitment guarantee) within the stipulated period. CG is an amount, equivalent to 10 per cent of the notified price of the annual coal requirement of the power firms, which the power companies have to deposit with the coal firms.
As per the notice 60 CPPs whose assurances have been cancelled include units of Bokaro Power Supply, Bhushan Power & Steel, Essar Power, Grasim Industries, JSW Aluminium, JK Tyre and Industries and Maharashtra Energy Development Agency. Also, CIL has withdrawn the authorisation of LoAs of Tata Power's 120 MW Unit V at Jojobera, Jharkhand and Durgapur Project's 300 MW Unit - 7A at Burdwan in West Bengal. Coal was to be supplied to these units CIL subsidiary Mahanadi Coalfields and Eastern Coalfields, respectively.