Illustrative image – not actual.
The CIDCO's project to increase the diameter of pipeline to Hetawane Dam from 1,200 mm to 1,500 mm is now facing roadblocks due to the widening work being carried out by NHAI on NH 66 and also from the forest department. The estimated cost of the project is Rs 67.90 crore.
CIDCO planned to lay new pipelines, which would have enabled it to draw an additional 50 MLD of water and resolve supply issues to Kamothe, Kharghar and Kalamboli,
The work for the project started in September 2014 and, till date, only 1.4 km out of 11.5-km pipeline has been laid, with just four months left for the March 2016 deadline.