Illustrative image – not actual.
The City and Industrial Development Corporation (CIDCO) Managing Director Dr. Sanjay Mukherjee presented the Budget of the nodal agency for financial year (FY) 2023-24 on 30 March, 2023.
The total size of the Budget is Rs 10,544.63 crore. The outlay is 21.79 percent more than the revised estimates for 2022-23.
The sector-wise allocation comprises housing (Rs 3,406.57 crore), development of Airport (Rs 907.52 crore), Metro rail projects (Rs 777.81 crore), Railway projects (Rs 381.35 crore), water supply projects (Rs 433.54 crore), and other priority areas.
Navi Mumbai Metro (NMML)
Navi Mumbai Metro Line-1 in its entirety is scheduled to be commissioned in April of 2023. The plans also entail designing and planning for the Metro Lines-2, 3, and 4.
Navi Mumbai Airport Affected Notified Area (NAINA)
The proposed city, NAINA will cover 174 revenue villages in Raigad district of Maharashtra, and spread over an area of 371 sq. km. There are 12 Town Planning Schemes (TPS) proposed for NAINA, with TPS-I being finally approved and TPS-II being provisionally approved. The budget estimate for the year 2023-24 is Rs 474.69 crore.
Navi Mumbai International Airport (NMIA)
To enhance connectivity to the upcoming airport and Mumbai Metropolitan Region (MMR), CIDCO has proposed the construction of bridges on the peripheral connectivity of NMIA over the Gadhi River and Ulwe river. Development of land in Sector-26, 27, 28, 29 and 30 at Pushpak Node, Navi Mumbai is also part of the plan.
Railway Projects
Among the six rail corridors, the Mankhurd-Belapur Rail Corridor, Belapur-Panvel Rail Corridor, and Thane-Turbhe-Nerul-Vashi Rail Corridor have already been developed by CIDCO. Currently, CIDCO is working on the Nerul/Belapur-Seawoods-Uran Rail Corridor.
The process of preparing the development plan is currently underway for an area of 92 sq. km comprising 32 villages, seven of which are in the Panvel Taluka and 25 in the Uran taluka of Raigad district.
PMAY Housing
CIDCO is constructing EWS/LIG tenements, totaling 86,588, in four separate packages, under Pradhan Mantri Awas Yojna (PMAY). Approximately 89,000 houses in Vashi, Juinagar, Kharghar, Ulwe, Mansarovar, Khandeshwar, New Panvel, and Taloja, with easy access to transportation networks, and essential services for residents.
Water supply
CIDCO has commenced the development of the Balganga Dam project with a capacity of 350 MLD. Additionally, the Kondhane Dam project which will meet the water requirements of NAINA and CIDCO area, is expected to be completed by 2027-28. CIDCO has proposed a budget of Rs 110 crore for FY24 towards land acquisition and rehabilitation.