Illustrative image – not actual.Pakistan has asked a Chinese company to
carry out, as soon as possible, the feasibility study of the Thar coal project
so that the mega project could be implemented on a fast track basis.
Pakistan’s Federal
Minister for Petroleum and Natural Resources, Mr Usman Aminuddin and a
three-member visiting delegation of Shenhua Group Corporation of China (SGCC) held
a meeting to discuss details of the project. The Chinese delegation is expected
to discuss technical details with officials of the Sindh Coal Authority (SCA)
and other provincial authorities. The petroleum minister told the delegation
that the government was focussing on Thar Coal reserves to meet the energy
needs through indigenous resources.
A Rs.100 million
Bankable Feasibility Study of Thar Coal Mining is currently in progress for a mine-mouth,
integrated coal-fired power project. SGCC would carry out feasibility and
technical reports of Thar coal on the basis of studies already completed by
Geological Survey of Pakistan (GSP) and SCA and handed over to Shenhua.
The Shenhua
group had demanded one out of four blocks in Thar coal field, with at least one
billion tonnes of coal reserves and details were being provided to the group.
Under the GSP study, Block I, II, III and IV have coal reserves of 3.56 billion
tonnes, 1.584 billion tonnes, 2.008 billion tonnes and 2.48 billion tonnes,
respectively.
The Shenhua
group has reported that Thar coal field possessed significant potential for
development but required a lot of preparatory work. It has advised
co-generation approach i.e mine-mouth power generation plant with associated
captive coal mine, as the priority development option. At a later stage, the
complex could produce coal briquettes to supply to the consumers in Sindh.
Around 175 billion tonnes of coal is spread over 9,000 sq km of Thar desert and the main coal bed thickness ranged from 12 to 21 metres at an average depth of 170 metres.