Illustrative image – not actual.China has refused to extend a US$ 50 million (approx. Rs.240 crore) loan to Pakistan for the US$ 1.5 billion (approx. Indian Rs.7,200 crore) Neelum-Jhelum hydel power project, asserting that it will not give more loans unless the ongoing projects are completed.
Pakistan is keen on launching the project immediately in order to ensure proprietary rights on the water of the Neelum river. India, on the other hand, wants to construct the Kishanganga hydel power project on the same river and for this purpose, it has plans to divert the current flow of water. If this happens, Pakistan will not be able to go ahead with the Neelum-Jhelum project, as the flow of water in Neelum river will not be enough to generate 963 MW of electricity.
Pakistan had sought an initial amount of US$ 50 million (approx. Rs.240 crore) from China to proceed with civil works, prior to initiating work on the mega project. Pakistan has also contacted Saudi Arabia, UAE and Kuwait for the requisite funds and is awaiting their response.
According to the 1960 Water Treaty, India is entitled to construct the dam only on the run of the river and cannot build the dam by diverting the flow of water of Neelum river. If India diverts the flow of water in a bid to generate electricity by establishing the proposed Kishanganga project, Pakistan will receive one-third less water of the total flow in Neelum river. This would definitely reduce the proposed installed capacity of the Neelum-Jhelum project.
Pakistan had floated international tenders for the Neelum-Jhelum project in 2000, whereas India did the same for the Kishanganga project in 2001.