Illustrative image – not actual.The work involves two-laning with hard shoulder of Kawardha-Rampur- Khamaria Road from the existing chainage 0.00 km to 28.09 km (design chainage from 0.00 km to 28.07 km) on EPC basis. The work will entail an investment of Rs 81.31 crore.
Another project being implemented involves two-laning with hard shoulder of Pamgarh-Bhilouni-Sasha-Sonsari-Jondhara-Lahod Road section from 0.00 km to 31 km. The work is being taken up at a cost of Rs 94.32 crore. With the latest information gathered by Projects Today, the above projects have been rescheduled for completion in December 2019.
A third project being taken up envisages four-laning of Ambikapur ring road from 0.00 km to 10.81 km at a cost of Rs 97.57 crore. The latest update with Projects Today reveals that the project has been rescheduled for September 2019.