Chennai Port-Maduravoyal elevated road troubled by slow rehabilitation processIllustrative image – not actual.

The Chennai Port-Maduravoyal elevated road is unlikely to meet its September 2013 deadline owing to tardy rehabilitation process along the river Cooum in Tamil Nadu.

 

Of the 7,100 families identified along the river for rehabilitation, the state revenue department has resettled only 1,100 families in Okkiyam Thoraipakkam. Also, the state government is yet to decide on evicting slum-dwellers along the route.

 

The Rs 1,655-crore project is jointly being implemented by the NHAI and the Chennai Port Trust with the support of the state revenue wing on BOT basis. Of the 890 columns proposed on the 19km stretch, only 30 have been progressing in the Koyambedu-Maduravoyal bypass, where the expressway takes an elevation. Each column gets five piles to support the grand structure, and about 580 piles have been completed on Chennai bypass road, while 370 piles are complete along the Cooum.