The Chennai Petroleum Corporation (CPCL), a subsidiary of the Indian Oil Corporation (IOC), is proposing to commission two major projects which entail investments worth Rs 2,208 crore during FY21.
The company has successfully completed the BS-VI DHDT revamp project from 1.8 to 2.4 million tpa in November 2019 with a new FCC gasoline desulphurisation unit of 0.6 million tpa capacity.
The pre-commissioning activities have already commenced and mechanical completion of the unit is expected during Q2/FY21. The commissioning is expected by Q3/FY21.
The new sulphur recovery block is expected to be mechanically completed by Q4/FY21. The estimated cost for the BS-VI auto fuels quality upgradation project is Rs 1,858 crore.
CPCL has also completed the Regassified Liquified Natural Gas (R-LNG) conversion project in one of the hydrogen generation units (HGU-214) by taking R-LNG as fuel and feed. R-LNG has been taken as fuel in refinery-III furnaces, three out of five gas turbines and three out of six utility boilers.
R-LNG conversion in balance gas turbines and utility boilers and HGU-205 is expected to be completed by Q4/FY21 in a phased manner. It had originally planned to complete by August 2020. The total cost of the project is about Rs 350 crore.
R-LNG conversion will have a positive impact on the carbon footprint with a reduction in CO2 emissions and reduce specific feed and fuel consumption for production of hydrogen.
The company is also coming up with nine million tpa refinery complex project at Cauvery Basin Refinery, Nagapattinam in Tamil Nadu. The environmental clearance (EC) for the project is in an advanced stage of review and approval by the Union Ministry of Environment, Forest and Climate Change.
In early June 2020, the CPCL board approved the incorporation of a joint venture (JV) for the Cauvery Basin project with IOC and CPCL together holding 50 percent stake in the JV.
The remaining portion will be held by financial institutions/strategic investors. CPCL can invest up to Rs 2,500 crore in the JV. While total project cost is estimated at about Rs 28,983 crore, the overall funding strategy is yet to be firmed up.