Illustrative image – not actual.Chennai Petroleum Corporation (CPCL) is planning to take up resid upgradation project near Chennai.
The Rs 3,110.36-crore resid upgradation project has been proposed to distillate the yield of the Manali refinery in order to maximise its margins. The draft final report has been completed and the investment approval has been obtained. The project is expected to be completed in 33 months from the date of the MoEF clearance, which is awaited. The clearance is delayed mainly due to a ban imposed by the MoEF on new expansion projects in the Manali industrial region.
CPCL’s 42-inch crude oil pipeline, as a replacement to the existing 30-inch crude oil pipeline from Chennai Port to the Manali refinery along the route of the proposed Chennai Port–Ennore connectivity road, is planned at an outlay of Rs 126 crore.