Chennai Metro Rail to commence tunnelling work in October 2023Illustrative image – not actual.

The Chennai Metro Rail has announced that tunnelling beneath Panagal Park in T Nagar will commence in October 2023. The tunnel boring machine (TBM) that will be used in T Nagar underwent a factory acceptance test on 01 April 2023.

The corridor has a 10 km underground section from the lighthouse to the ramp at the Kodambakkam power plant.

The TBM launching shaft is being built at Panagal Park and is expected to be ready for lowering and assembly in October 2023. The TBM will build tunnels 29 mtr below ground level from Panagal Park to Nandanam, with the purpose of completing the boat club by September 2024.