Chennai Metro Rail Phase-2 construction on trackIllustrative image – not actual.
Chennai Metro Rail (CMRL) has begun procuring critical equipment required for driverless train, to get the 118.9 km lines of Phase-2 ready in less than five years. 
 
In October 2021, CMRL floated four tenders to procure tracks, overhead equipment (OHE), telecommunication and other systems required for remote monitoring and control and efficient train operations. 
 
During the Tamil Nadu state budget, it was announced that Phase-2 Metro Rail project will be completed by 2025. Already, preconstruction and construction on ground have commenced within the city and at suburban localities that will be linked on Corridor-3 from Madhavaram to Siruseri Sipcot and Corridor-4 from Light House to Poonamallee. 
 
The major tenders floated in include tracks for Corridor-5 between CMBT and Elcot and for Corridor-3 between Sholinganallur and Sipcot as well as for stabling or parking trains after daily service.  
 
Tenders were floated for procuring and installation of OHE, which will supply power to the driverless trains, along Corridor-3 between Madhavaram Milk Colony and Sholinganallur and on Corridor-5 from Madhavaram to CMBT and for the depot at Madhavaram. 
 
Other tenders include design, installation and commissioning of telecommunication radio systems needed for train operations and other systems like SCADA or supervisory control and data acquisition, a software that allows remote monitoring and control of all the systems. 
 
The procurement comes at a time when on ground piling work to build the foundation pillars for elevated lines have started in Porur and pre-construction work has commenced in other locations including Poonamallee, Purasaiwalkam, Thiruvanmiyur, Adyar and Royapettah.  
 
Over half of the 19 construction tenders floated are either awarded or in final stages while the rest are on various stages of the process.