Rail Vikas Nigam (RVNL) has received three letters of acceptance (LoA) from Chennai Metro Rail (CMRL) for the construction of underground stations of Corridor-3 for the Phase-II project.
Among these three orders, the first order involves the construction of five underground stations at KMC (Kilpauk), Sterling Road JN, Nungambakkam, Gemini (Anna Flyover), Thousand Lights and Thousand Lights crossover box and the works of two underground stations at Royapettah government hospital (Roy Apettah) and Chetpet Metro of CMRL under Phase-II.
The construction of these five underground stations, which costs Rs 1,730.6 crore, is expected to be executed in 57 months from the appointed date.
Similarly, the second order is to construct four underground stations at Dr. Radhakrishnan Salai, Thirumayilai, Mandaiveli and Adyar Junction and two cross passage shafts and one emergency escape shaft and the works other than the diaphragm wall of one underground station at Greenways Road Metro. In addition, the order, costing Rs 1461.9 crore, is expected to be executed in 52 months from the appointed date.
The third order includes the construction of three underground stations at Adyar Depot, Indira Nagar and Taramani Road Junction (Taramani) and ramp and works other than the diaphragm wall of an underground station at Thiruvanmiyur Metro.
Furthermore, the third order worth Rs 865.62 crore, is anticipated to complete in a time span of 54 months.