The Chennai Metro Rail (CMRL) has started the work to build a tunnel for the Phase-II project in the stretch between Greenways Road and Mandaveli.
Greenways Road is a key location in the 116-km long Phase-II project, and it is a part of Corridor-III, which starts at Madhavaram and terminates at SIPCOT. The areas covered include Perambur, Purasawalkam, Sterling Road, Adyar, and Sholinganallur.
Among the stretches which will be opened at the end of the project is Greenways Road to Thirumayilai via Mandaveli in 2028. Of the four tunnel boring machines (TBM), two will be used to construct a tunnel from Greenways Road to Adyar junction, and two from Greenways Road to Mandaveli. The TBM will cover about 750 mtrs. and the machine will be boring at a depth of about 17 mtrs.
In February, 2023, TBM named ‘Kaveri’ began the tunnelling process towards Adyar. More recently, the TBM named ‘Noyyal’ was launched at Greenways Road to build a tunnel towards Mandaveli. One more TBM ‘Vaigai’ will start work in a few weeks’ time.
The contractor to build the stations on it has been finalised recently. In the remaining two corridors of the project, Light House to Poonamallee (Corridor-IV) and Madhavaram to Sholinganallur (Corridor-V), construction work has been progressing at a steady pace.