Chennai Metro completes casting of U-girders for Corridor 5 elevated sectionIllustrative image – not actual.

Chennai Metro Rail (CMRL) has completed the casting of all 824 U-girders required for the 13.1-km elevated stretch of Corridor 5 under its Phase 2 expansion project, marking a step in the development of the corridor connecting Madhavaram Milk Colony and Sholinganallur.

The final U-girder, measuring 19.5 mtrs. in length and intended for the Adambakkam Metro station, was cast at the C5 ECV-02 casting yard. Completion of girder production is expected to accelerate superstructure construction activities along the 47-km corridor. The 43-acre casting yard, one of the largest precast facilities established for the Phase 2 network, has been producing key structural components for elevated viaducts and stations. Package C5-ECV-02, being executed by Larsen & Toubro, covers approx. 12.431 km between CMBT Metro Station and Puzhuthivakkam Metro Station and includes the construction of 12 elevated stations, special spans, and related infrastructure.

The achievement builds on another landmark reached in June 2025 when CMRL erected India’s first 33.33-mtrs.-long U-girder at Ramapuram under the same package. The milestone reflects steady progress in Chennai’s Metro expansion programme aimed at enhancing urban mobility and connectivity across the city.

← All latest storiesBack to top →