Illustrative image – not actual.Chennai Water Desalination, a subsidiary of IVRCL Infrastructure & Projects has decided for an additional borrowing to meet the cost escalation of the Minjur water desalination project.
The company, which is implementing the 100 MLD seawater desalination plant, originally planned the project at a cost of Rs.470 crore, but due to cost escalation, is now expecting to complete the project at a cost of Rs.550 crore. DEG Bank of Germany is to come in with the additional lending of 14 million euros (Rs.80 crore). DEG is the fourth lender, after Canara Bank, United Bank of India and Indian Overseas Bank for the project.
The Chennai Metropolitan Water Supply and Sewerage Board (Metrowater), for which the company is setting up the plant on a DBOOT basis, has approved the borrowing to meet the cost escalation.
Originally, the the project was to go on stream in June 2008 and commercial operations from August 2008 in stages. But the marine work for laying the intake pipeline could not be taken up because of adverse sea conditions. So now, the project is re-scheduled for completion by end August 2008. Instead of stepping up production in phases, the plant will start at full capacity. Trial commissioning is expected to go on between September and December 2008. It will start producing freshwater from seawater from January 2009.
Related Links:
Project profile