Chennai desalination plant delayedIllustrative image – not actual.

While the Chennai Metrowater has completed its job of laying a 30 km pipeline from Red Hills to Minjur desalination plant, IVRCL Infrastructures and Projects is yet to complete the construction of a 100 mld desalination plant.

So far, IVRCL has completed the construction of various units such as sand filters, cartridge filters and reverse osmosis units. However, offshore construction comprising the laying of a separate pipeline to draw seawater from 10 mtrs depth below sea level and discharge waste water is yet to be completed.

The 30 km Red Hills-Minjur pipeline is funded under JNNURM and completed at a cost of Rs.93 crore. The work also comprised construction of a pumping station and underground tank each at Minjur and Madhavaram and six million ltrs capacity underground tank in Red Hills.

While the facility at Minjur will be used to receive water from desalination plant and transport to Red Hills, the pumping station and underground tank at Madhavaram will also be utilised to supply water to Madhavaram municipality as part of the comprehensive water supply scheme. Similarly, an underground storage with a capacity of 2.5 million ltrs has also been built to supply drinking water to Manali.

Chennai Water Desalination, a SPV formed by IVRCL Infrastructures and Projects, has been is setting up the project on DBOOT basis.