Illustrative image – not actual.Shyam Energy is likely to finalise the contractor for electro-mechanical works for its 6 MW Chel-II hydro electric power project near right bank of Chel Khola in Darjeeling district of West Bengal by April 2008. Currently, the tendering process is underway.
Bids from contractors for the electro-mechanical works (design, manufacturing, supply, erection, testing and commissioning) were invited in August 2007 and around six entities responded to the tenders in January 2008.
The proposed 3x2 MW power project will entail an investment of around Rs.50 crore. The company has already signed a power purchase agreement with West Bengal State Electricity Board. Work on the project is likely to commence by June 2008 and full completion of the project is expected by 2009.
In addition to this, Shyam Energy also plans to set up a 6 MW hydro electric power unit at Garubathan in Darjeeling for, which Delhi based Dr. Hutarew & Partner (India) is appointed as a consultant.