The Pakistan government has allocated Pakistani Rs.3.1 billion for Chashma Right Bank Canal (CRBC) project. The Executive Committee of the National Economic Council (ECNEC) had deferred the project for want of resources. The project is expected to be completed in 2004.

Water and Power Development Authority (WAPDA) has estimated the cost of the project to be Pakistani Rs.17.6 billion including Rs10.3 billion foreign exchange component. It may be noted that the project was estimated to cost Rs1.5 billion in November 1978. The revisions in the project cost are tabled below.

Year

Cost  (Rs. billion)

November 1978

1.5

February 1982

3.4

November 1991

10.2

January 1998

13.8

April 2001

17.6

The Chashma irrigation is an ongoing project, which envisages the construction of a 170 mile long canal taking off from the right bank of the Chashma Barrage at River Indus and 700 mile long distributaries and minor canals.

An investment of Pakistan Rs.13.9 billion has already been made to complete 76 per cent of the project. The major parts of the project which have been completed include a 52-mile long canal with a capacity of 1,226 cusecs, 52 mile long canal, 24-mile long CRBC with 800 cusecs capacity and the construction of CRBC's 94 miles main canal with traverses 30 miles in Dera Ismail Khan and 64 miles in Dera Ghazi Khan.