Chashma Hydro electric power plant inaugurated in PakistanIllustrative image – not actual.

The President of Pakistan, Mr. Rafiq Tarar inaugurated the 184 MW Chashma Right Bank Hydro Electric Power Plant at Chashma, 20 km from Mianwali in Pakistan, on 27 February 2001. This is Pakistan’s first bulb hydro project and is expected to meet power requirements, particularly during peak hours.

 

This hydel plant built on the right bank of River Indus, comprises 8 bulb type turbine units, each of 23 MW.

 

The plant has been set up at a cost of Pakistani Rs.17.8 billion. Water and Power Development Authority (WAPDA) has financed 60 per cent of the project cost, while the foreign currency component of $245 million has been financed by Asian Development Bank, French Credit and Citi Bank of Japan.

 

The project has been designed and supervised by Chashma Group of Consultants comprising SOGREAH and CNR of France, ACE, NESPAK and MAES of Pakistan. The contractors for the project were a joint venture of Hyundai of Korea and Hakas of Pakistan for civil works, Marubeni of Japan for mechanical works and ALSTOM of France for electrical works.


Work on the project had started in December 1994 and was expected to be completed by end of December 1998. But in 1996, due to financial constraints, work was stopped for a period of 26 months. Later, in 1999, after arranging for the required local currency, the work was resumed.


According to the revised schedule for completion of the project, two units were commissioned in December 2000 and one unit in February 2001. These units were inaugurated by Mr. Tarar. The other units are expected to be operative within the next four months.

 
According to Mr. Tarar, Pakistan has a good network of barges and a potential to generate 40,000 MW of hydel power.