Chandu Budhera WTP expansion nears completionIllustrative image – not actual.

The fifth 100 MLD unit at the Chandu Budhera Water Treatment Plant (WTP) in Gurugram is scheduled to begin trial operations next week.

The new unit will increase the plant's total treatment capacity from 400 MLD to 500 MLD and is expected to improve water supply to Sectors 81 to 115.

The Rs 52.50 crore expansion project commenced in March 2024 and was scheduled for completion by April 2026. However, commissioning was delayed due to the pending electricity connection. With the power connection now in place, pre-commissioning tests of machinery and equipment are currently underway.

Meanwhile, the Gurugram Metropolitan Development Authority (GMDA) is planning a further capacity expansion at the facility. The tender for the sixth 100 MLD unit is currently under technical evaluation. In addition, the Haryana Government has approved Rs 149 crore for the construction of a third 100 MLD water treatment plant at Basai, which is expected to be completed by early 2029.

← All latest storiesBack to top →