Illustrative image – not actual.BHEL is likely to bring on stream the Unit VII of DVC's Chandrapura super thermal power project (STPP) by 31 August 2009 in Bokaro district of Jharkhand.
Unit VII and VIII each with a 250 MW capacity have faced lot of hurdles in commissioning, primarily, due to the slow pace of civil works and insufficient mobilisation of men, material and resources by National Buildings Construction Corporation (NBCC), which is the subcontractor, appointed by BHEL, for execution of civil and structural works for the project.
BHEL's scope of work included the manufacture, supply and commissioning of steam turbines, generators, boilers and associated auxiliaries, besides installation of electrical controls and instrumentation, electrostatic precipitators and switchyard.
The Union Ministry of Power has also advised DVC to actively follow up with BHEL for timely completion of the project.