Chandrapur power project gets environmental clearanceIllustrative image – not actual.

The MoEF has granted clearance on September 04, 2008 for the coal based power project at Ghuggus of Chandrapur district in Maharashtra. The power plant coming up in 2 units of 60 MW each is being implemented by Gupta Coalfields & Washeries at a total investment of Rs.657 crore.

The power project will spread over 56 ha of which 24 ha will be used for the plant, 14 ha for ash pond, 4 ha water reservoir and 14 ha under greenbelt. Land has been acquired for the project.

The company has achieved financial closure for the project. It has signed a PPA with Tata Power Trading Co. and has awarded the EPC contract worth Rs.650 crore to Maytas Infra.

Boundary work for the project is currently underway. The first unit will take 20 months for completion while the second unit will be completed in 22 months.