Illustrative image – not actual.After a delay of four years, the Chanchalguda–Santoshnagar steel flyover is now scheduled for completion by June, with the Greater Hyderabad Municipal Corporation (GHMC) projects wing accelerating construction following the acquisition of key properties.
Officials stated that around 82 percent of the physical work has been completed, including major foundation activities and the shifting of HMWSSB pipelines and electricity lines. The 2.5 km four-lane flyover will connect Chanchalguda to Santoshnagar, with the main ramp starting near Yadagiri Theatre. An additional up-ramp is being constructed at Saidabad and a down-ramp at IS Sadan to improve traffic flow. The project is expected to significantly ease congestion for commuters travelling to and from Malakpet, Saidabad, I.S. Sadan, Champapet, Karmanghat and surrounding areas.
The flyover project began in 2020 and was initially planned for completion within two years. However, progress was delayed due to property acquisition challenges and land-related issues. With these hurdles now resolved, officials said construction is moving at a brisk pace to ensure the flyover is ready for public use by the end of June.