Illustrative image – not actual.CESC is likelyto commission its 2x300 MW coal based power plant in Haldia, West Bengal by 2014.
The project isbeing implemented by CESC’s subsidiary Haldia Energy (HEL). The company hasshortlisted two private equity (PE) firms to raise Rs 1,000 crore for threeprojects of its subsidiary Haldia Energy (HEL). The company is looking todivest upto 20 percent stake in HEL. The total investment for the three project— Haldia(2x300 MW), Orissa (2x660 MW) and Maharashtra(600 MW) — is expected to be about Rs 13,000 crore. HEL has already acquired448 acre for the power project which is slated to be ready by 2014. Around 350acre has been identified for Phase I of 320 MW power plant at Danro inJharkhand. The company has already acquired 772 acre at Denkanal in Orissa. Theproject plan has been finalised and all the requisite clearances, includingenvironmental clearance, have been obtained for the Orissa power plant.
Meanwhile, thecompany has sought for fresh linkage supplying lower grade coal from the UnionMinistry of Coal and CIL.