Illustrative image – not actual.CESC has finalised Katikund in Dumka district of Jharkhand as the location for the in1,000 MW pithead thermal power project.
The company had signed a memorandum of understanding (MoU) with the NDA-led Arjun Munda government in September 2005 for the proposed project. In the MoU, CESC had offered three alternative sites to the Jharkhand government - at Godda, Latehar and Chandil - to locate the project, of which only the Godda site was near a pithead. The Katikund pithead site was decided upon later.
The project, to come up at a cost of around Rs.5,000 crore, will now be implemented in two stages of 500 MW each, instead of the earlier plan of two plants of 250 MW each in the first stage, followed by another with 500 MW capacity later on. CESC will apply for the coal block to the Union coal ministry after obtaining the necessary state recommendation.
While the first 500 MW unit is expected to come up within in 36 months from the date all clearances are obtained, the second unit (500 MW) unit will be completed in another six months' time.
Also See:
CESC plans SPVs for three power projects (19-Dec-06)
Related Links:
Project profile