Calcutta Electric Supply Company (CESC) has reportedly acquired 100 per cent ownership in Dhariwal Infrastructure by snapping the remaining 50 per cent stake for around Rs 100 crore.

CERC is expected to shortly seek approval from the Registrar of Companies to rechristen Dhariwal Infrastructure, which is now a wholly-owned subsidiary.

Dhariwal is executing the Rs 3,000-crore greenfield thermal project at Chandrapur in Maharashtra The 2x300 MW project will be executed in 36 months from the zero date. The Unit I 300 MW unit will come up in 33 months by March 2013. Also, CESC is likely to finalise the Rs 1200-crore EPC contract soon.