CERC to fine power generating companies for unused transmission linesIllustrative image – not actual.
The Central Electricity Regulatory Commission (CERC) has directed power-generating companies to pay transmission and relinquishment charges for stranded transmission capacity resulting on account of abandoned projects.

The relinquishment charges will be paid for abandoned lines, as they are not using it to supply power round the clock. Most of the stressed units have also shifted their transmission plans because they changed their consumer or decided to sell power in the open market.

The Central Transmission Utility (CTU) is charging approximately Rs 40 lakh per MW as relinquishment charges from any generating company that surrenders transmission network due to either lack of power demand or change of power supply plan.

These charges are levied for a period of 12 years counting it as stranded. The power companies affected by the relinquishment charges are in north, east and west regions and include Essar Power, Jindal India Thermal Power, Jaiprakash Ventures, GMR Energy, Lanco, MB Power, KSK Mahandi and others.

These are same power companies facing or about to face insolvency proceedings. The CERC has also directed CTU to create a separate account for the relinquishment charges and it should be used to discount transmission charges for the existing long-term and medium-term consumers on that same transmission line.