Illustrative image – not actual.The Central Electricity Regulatory Commission (CERC) has approved the revised guidelines for the grant of interstate transmission system (ISTS) connectivity to renewable energy projects.
The Commission had issued draft amendments to the earlier procedure on 24 July 2020, and invited suggestions from the stakeholders on the proposed changes.
As per the revised guidelines, the procedure will apply to central transmission utility (CTU), regional load dispatch centers (RLDCs), state load dispatch centers (SLDCs), state transmission utility, concerned distribution companies (DISCOMs), and implementing agencies.
Applicants whose generation capacity is already connected to the grid (ISTS or intrastate transmission system) or for which connectivity is already granted cannot apply for additional connectivity for the same generation capacity. A new application for additional generation capacity should be submitted.
The CTU will grant Stage-I connectivity within 60 days of the month’s last date in which the application was submitted. If capacity at the location where
Stage II connectivity will be granted to an entity that has been issued the letter of award (LoA) or has entered into a power purchase agreement (PPA) with a renewable energy implementing agency or a distribution licensee consequent to tariff-based competitive bidding.
The renewable hybrid generating projects, including round-the-clock hybrid projects, will be eligible for separate stage-II connectivity for each location based on the same PPA.
After grant of Stage-II connectivity, the grantees must achieve--ownership or lease rights or land use rights of the land, financial closure with sanction letter from a financial institution and proof of release of funds supported by auditor’s certificate.
As per the revised regulations, the generator pooling station’s planned capacity should be less than the dedicated transmission line’s capacity required to be provided as per the grant of connectivity. The minimum aggregate evacuation capacity of the generator pooling station should not be less than 100 MVA.
The Commission had issued draft amendments to the earlier procedure on 24 July 2020, and invited suggestions from the stakeholders on the proposed changes.
As per the revised guidelines, the procedure will apply to central transmission utility (CTU), regional load dispatch centers (RLDCs), state load dispatch centers (SLDCs), state transmission utility, concerned distribution companies (DISCOMs), and implementing agencies.
Applicants whose generation capacity is already connected to the grid (ISTS or intrastate transmission system) or for which connectivity is already granted cannot apply for additional connectivity for the same generation capacity. A new application for additional generation capacity should be submitted.
The CTU will grant Stage-I connectivity within 60 days of the month’s last date in which the application was submitted. If capacity at the location where
Stage II connectivity will be granted to an entity that has been issued the letter of award (LoA) or has entered into a power purchase agreement (PPA) with a renewable energy implementing agency or a distribution licensee consequent to tariff-based competitive bidding.
The renewable hybrid generating projects, including round-the-clock hybrid projects, will be eligible for separate stage-II connectivity for each location based on the same PPA.
After grant of Stage-II connectivity, the grantees must achieve--ownership or lease rights or land use rights of the land, financial closure with sanction letter from a financial institution and proof of release of funds supported by auditor’s certificate.
As per the revised regulations, the generator pooling station’s planned capacity should be less than the dedicated transmission line’s capacity required to be provided as per the grant of connectivity. The minimum aggregate evacuation capacity of the generator pooling station should not be less than 100 MVA.