Centre urges state govt to fast track Aluminium Park projectIllustrative image – not actual.

The Centre has urged the Odisha government to expedite completion of the Aluminium Park at Angul by March 2018.

The progress was found to be poor considering that the fund was provided to the project around 18 months ago. The physical progress of the project is 1.82 percent while the financial progress is Rs 1.57 crore.

The project was expected to be completed in two years as projects under Modified Industrial Infrastructure Upgradation Scheme (MIIUS) are completed by that time.

Central PSU, National Aluminium Company (Nalco) and state PSU, Industrial Infrastructure Development Corporation (IDCO) are developing the project on 223 acre. The proposed park will be the first project in the subcontinent with a facility to directly obtain molten aluminium from the smelter.

The project was approved under the MIIUS of DIPP in August 2015.

 