Centre to revise model concession agreementIllustrative image – not actual.

The government is preparing for large-scale tinkering of a so-called model concession agreement (MCA) used by Union government-owned ports while granting rights to private firms for developing cargo-handling facilities, as it looks to boost investor sentiment in the sector through better allocation of risks between the government and the private firms amid slowing global trade.

A concession agreement sets out the terms and conditions of a port contract.

The MCA that is followed currently mandates that a private developer handles a minimum guaranteed cargo (MGC) every year specified in the 30-year contract. Failure to achieve the prescribed MGC for three consecutive years can lead to termination of the contract.

The government plans to replace MGC with a minimum guaranteed revenue (MGR) that a private developer has to pay the port authority for each year of a 30-year contract. In case gross revenue from operations falls short of MGR in a year, the private developer can make good the shortfall by paying from his pocket or let the project go into default and subsequent termination if the shortfall occurs for three consecutive years.

The MGR will be revised every year to account for inflation because it is indexed to the Wholesale Price Index (WPI) to the extent of 60%, according to the revised MCA drafted by the shipping ministry.

For a multi-cargo terminal, the MGR gives more flexibility. Even if the facility is not doing well in one particular cargo, it is able to do it in some other cargo which has a higher tariff.

The MGR clause will kick in only when the revenue falls below MGR. If the gross revenue from the facility exceeds MGR, the developer will have to pay a share in the revenue to the government port at a rate determined through a bidding process.

The new model concession agreement will provide for renegotiating the concession period either by compressing the 30-year period or extending the term if the actual average traffic exceeds the target traffic or falls short of it by more than 20%.

Any increase in the tenure of the concession period will be capped at 10 years in case an increase is necessitated due to lower traffic. However, a reduction in concession period due to higher volumes will be capped at three years.

The private developer may opt to pay a further premium equal to 10% of the gross revenue in lieu of a reduction in concession period.


 