Illustrative image – not actual.The Union ministry of surface transport plans to review pre-qualification norms for World Bank-funded road projects.
Domestic construction companies had felt that the
pre-qualification criteria specified by the National Highways Authority of
India (NHAI) were very strict. This had made it difficult for them to bag
contracts. This was especially true for projects funded by international
agencies.
Following directives from the ministry, the NHAI had relaxed
some of the criteria after consulting the World Bank. A contractor had to have
turnover that is twice the estimated cash flow per annum from the project. This
was relaxed from the earlier criterion of 2.5 times. In the case of a joint venture,
the ministry had stipulated that each partner should meet 25 per cent of the
qualifying criteria instead of the earlier 30 per cent. The amount of bid
security was also reduced from two per cent to one per cent of the contract
size.