Illustrative image – not actual.The Empowered Group of Ministers (EGoM) is planning to get all-at-a-time clearance for infrastructure and hydel projects in Arunachal Pradesh.
The power ministry is looking forward to getting environment and forest clearance as well as simultaneous approval instead of sequential approval for land acquisition and preparation of detailed project reports (DPRs) for supporting infrastructure projects like roads and bridges.
About 94 hydel-based projects, having a capacity of 41,702 MW, have been allocated by the state to private and public developers for implementation. But most of these projects, like highways and bridges, have been delayed due to lack of infrastructure for transporting heavy equipment and machinery to project sites.
The ministries of defence, road transport and highways (MoRTH), power, as well as the ministry of development of North-Eastern region (Doner), have been given the task to find out ways to expedite development of supporting infrastructure for the number of hydel projects coming up in the state.
Arunachal Pradesh has about 50,000 MW hydro-power potential spread over eight river basins including Sian, Kameng and Subansiri hinges. Out of the 50,000 MW, the state has harnessed just 405 MW, while projects totalling 2,710 MW are under construction.
Besides, in order to fast track the projects, the EGoM has called a meeting with the ministries and is expecting to get approval from the Election Commission for its proposed meeting.
If the projects are given sequential clearance (i.e. forest clearance and then the environmental one) many of these projects are likely to be completed by 2022.
While the MoRTH, Doner and Power ministry are supporting all-at-a-time clearance, the MoEF is supporting sequential clearance as it feels the proposed projects will demand large scale diversion of forest land.