Centre scraps EoI for box transhipment hub at KanyakumariIllustrative image – not actual.

The Central government has scrapped plans to build a container transhipment hub near Kanyakumari through public-private partnership (PPP) route following opposition from local fishermen groups.

On 22 February 2021, the Centre-owned VO Chidambaranar Port Trust (VOCPT) floated an expression of interest (EoI) from port developers and shipping lines to build 6.5 million TEUs capacity transhipment hub, based on a direction from the ministry of ports, shipping and waterways.

Potential bidders were given time until 20 March 2021 to file their expression of interest. However, on 15 March 2021, the District Collector of Kanyakumari wrote a letter to VOCPT, conveying that he had received representation from local fishermen groups raising their concerns over the EoI for the container transshipment hub.

On 18 March 2021, the Centre advised VOCPT to cancel the EoI floated for development of a transshipment hub near Kanyakumari.

In July 2016, the Union Cabinet accorded in-principle approval for building a new major port at Enayam (westward to Coalchel and located between Helen Nagar and Melakurumbanai village) in Kanyakumari in three phases with an investment of Rs 27,570 crore to handle 127 million tonne of cargo a year.

But following the resistance from local fishermen groups, a new site which is closer to Kanyakumari, nestled between Kovalam and Keelamanakudi villages, was identified to minimise opposition to the project.

VOCPT currently has two container terminals with a capacity to handle 1.17 million TEUs. The two terminals handled 8,03,719 TEUs in FY20, recording a strong nine percent Y-o-Y growth in container traffic, setting itself up as a strong candidate to be declared as India’s transhipment hub.

VOCPT has drafted a road map for the port’s transition into a transshipment hub by 2025. This involves converting Berth No 9 into a PPP run container terminal to handle 0.6 million TEUs with an investment of Rs 480 crore.

Further, berths 1,2,3 and 4 are planned to be converted into container terminals to handle 1.76 million TEUs with an investment of Rs 2,696 crore. Another 4.1 million TEUs capacity will be created in the port’s outer harbour with an investment of Rs 3,744 crore.

 