Centre nod for Ganga riverfront development project Phase-IIIllustrative image – not actual.

The union water resources minister Nitin Gadkari has approved the second phase of Ganga riverfront development project.

The project envisages development of 27 ghats between Nauzar Ghat and Nurpur Ghat in Patna, and a 6.5 km promenade connecting them. The project will incur an estimated expenditure of Rs 218 crore.

Work on the first phase of the Ganga riverfront development project is in the final stages.

Phase-I entails development of the 5.7 km long and 15 ft wide walkway along 20 ghats in the city which will have amenities like decorative street lamps, public lavatories, 500 seating benches and green cover.

The project was initially slated to be completed by June 2016, but the deadline was later extended to June 2018.

The centre has sanctioned Rs 22,000 crore for different schemes under Namami Gange.