The Ministry of Power is working with public and private financial lenders along with NTPC to finalise a warehousing model plan for the revival of 45,000 MW power assets.

The plan will be finalised by the end of July 2018. It will involve lenders such as PFC, REC and other banks along with NTPC that will house stressed power projects.

The revival of stressed assets will be undertaken in a couple of years by signing power purchase agreements (PPAs) with CPSUs and later selling them as profitable assets after the demand picks up.

The government will have a majority stake of around 51 percent in these projects which will allow them to have the ownership and give the rights to change the promoter and management hands.

The government will help in running these plants, providing finance and help them improve the financial position for a couple of years and sell them after the demand for power gains momentum.

In the initial phase, there will be around 25,000 MW projects with no PPAs or fuel linkages that will be housed under the warehousing model.

However, the plan will be open for other 20,000 MW projects that have fuel linkages tied up but are facing problems in servicing the debt.