Illustrative image – not actual.The Union government has approved the increase in the concession period for ten National Highways Authority of India (NHAI) projects worth Rs.12,465.65 crore.
At present, the concession period for long-term projects is normally 20 years, including a three-year construction period. Now in the case of these ten projects, the government has increased the concession period up to 25-30 year period.
The decision will enable the private concessionaire to collect toll for a longer period of time. With the increased scope of revenue generation, there will be lesser risk for the participant and will also make projects more viable.
Besides, with government also revising the cost of the projects upwards, the private concessionaire will now be able to access more government grants, even as it is capped at 40 per cent of the project cost. NHAI provides an upfront grant of 20 per cent at the time of commencement of the project and the balance 20 per cent is given during the maintenance phase. NHAI recently increased the cost of the projects by 10 per cent for which the DPR was prepared in 2007. DPR of the project which was prepared before 2007, has been revised upwards by 20 per cent.
The details of the projects are given in the table below:
|
Project Name |
Revised Concession (in yrs) |
Revised Cost (in Rs. cr) |
Original Cost (in Rs.cr) |
|
Kundapur-Suratkhal section |
25 | 891 | 616 |
| Tirupati-Tiruthani, Chennai | 30 | 922.6 | 802 |
| Kuttipuram-Edapally section | 30 | 1,643.20 | 1,158 |
| Pune-Sholapur | 21 | 965.3 | 923 |
| Coimbatore-Mettuplayam | 29 | 582.25 | 293.4 |
| Muzaffarnagar-Dehradun | 20 | 1,516.42 | 1,306 |
| Patna-Buxor | 25 | 1,757.40 | 1,620 |
| Khagaria-Bhaktiarpur | 29 | 1,766.30 | 1,704 |
| Ghaziabad-Aligarh | 24 | 1,570.18 | 1,325 |
| Amritsar-Pathankot | 20 | 851 | 658.52 |