Illustrative image – not actual.The Union government has approved a revised cost estimate of Rs 30,436.95 crore at 2023 price levels for Phase-I of the Polavaram Irrigation Project in Andhra Pradesh.
Under the approved framework, the balance Central grants are capped at Rs 12,157.53 crore, with the project targeting water storage up to an elevation level of +41.15 metres. The Centre has released Rs 12,620.53 crore in assistance over the past five financial years to accelerate civil and rehabilitation works. Engineering progress has advanced across major components, with concrete work on the main spillway at 98.84%, earthwork at 96.87% and steel work at 92.95%. Of 96,660 project-displaced families, 17,892 Phase-I families have been physically shifted.
The government has approved completion by March 2026, with provision for a one-year extension, supporting continued infrastructure and rehabilitation activities.