Centre approves Nalgonda thermal power projectIllustrative image – not actual.
The Union Ministry of Environment and Forests accorded permission to the Telangana government to set up a thermal power project on 5,000 acre of forest land.

 

However, the state government had asked for 10,000 acre of land at Dilavarpur village of Damaracharla, in Nalgonda district to construct the project with an installed capacity of  6,800 MW.

 

The ministry informed the state government that the project did not require more than 5,000 acre of land. This was based on the DPR (Detailed Project Report) and the same was accepted under stage-I clearance.

 

In addition, the state government should compensate Rs 160 crore for the acquired forest land through the transfer of equivalent revenue land to the forest department.

 

More Project Info:
Damaracherla Coal Based Power Project

← All latest storiesBack to top →