Illustrative image – not actual.The Ministry of Urban Development has approved two projects for Mysore in Karnataka. The identified projects are Remodeling of Storm Water Drainage System and development of an Integrated Solid Waste Strategy project under the JNNURM.
The Remodeling of Storm Water Drainage system project will be implemented at an estimated cost of Rs.100 crore, of which the Centre's share will be Rs.80 crore. An amount of Rs.20 crore will be released as the first installment. The city has six catchments with 76 drains with primary drain network of 44.60 km, secondary drain network of 79.12 km with total network covering 123 km of length in the city.
The Integrated Solid Waste Strategy project will be implemented in 18 months, at a cost of Rs.29.98 crore, of which the Centre will contribute Rs.23.98 crore. An amount of Rs.5.99 crore will be released as the first installment.