Illustrative image – not actual.The Central Railway has plans to undertake replacement work on 6 road-over-bridges (R-O-B) over railway tracks and complete the work within 5 years.
The bridges which would be taken up are as follows:
bridge
|
location |
Work |
|
Hancock |
Sandhurst
Road station |
Reconstructed
|
|
Carnac |
Chhatrapati
Shivaji Terminus |
Reconstructed |
|
Byculla |
Byculla
station |
Reconstructed
|
|
Eastern
Express Highway |
Mulund-Thane |
Recasting
of slabs |
|
Reay Road |
Reay Road |
Recasting
of slabs |
|
Mankhurd |
Mankhurd |
Recasting
of slabs |
Besides the above 6 R-O-Bs, 7 other bridges would be
replaced in the next 10 years. These are Garden bridge at Byculla, Arthur
bridge between Byculla and Chinchpokli, Olivant bridge between SandhurstRoad
and Byculla, Carol bridge near Parel, Chunabhatti, Chembur and Govandi
over-bridge.
The cost of all 13 bridges would be shared equally by
both the Central and the state governments.
Work on the project is expected to start soon. The
work would include removing the hutments and dwellers on the pavements. This