Central govt’s projects in Meghalaya delayed Illustrative image – not actual.
Undue delay in implementing central projects worth over Rs 7,000 crore in Meghalaya has resulted in an additional cost overrun of nearly Rs 2,000 crore.

The six central projects in Meghalaya had a cost of Rs 7,108.02 crore and the completion cost of these projects is Rs 9,025 crore, therefore implying a cost overrun of Rs 1,916.98 crore.

A railway line from Shillong connecting the rest of the country, covering a length of 108 km entailed an investment of Rs 6,000 crore.

Work on the North Eastern Indira Gandhi Institute of Health and Medical Sciences is underway where regional cancer center, the medical college building, the hostel and nursing college is proposed to come up.

The cost of the project is approximately Rs 280 crore.