Illustrative image – not actual.With the approval in place from the central government, the solar power plant will become functional by 2021.
In order to speed up the project work, the centre will clear all the land acquisition hurdles. The project requires 1,024 ha, out of which 825 ha has been purchased by Maharashtra State Power Generation Company (MAHAGENCO). The remaining land will soon be acquired from Methi and Vikaran villages.
The project will be completed in two phases and will cost about Rs 160 crore. The first phase of 250 MW will be functional in 2019 and the second phase in FY 2021-22. MahaTransco has taken the mandate for laying the transmission wires for the project to supply power to the farmers.
The Maharashtra government is also looking at setting up a solar energy park in Dhule.